How long the NAD division's districts take to approve a mitigation bank, what credit supply they oversee, and how the districts differ from one another. The clock that matters is the regulator's own — everything else includes time the applicant spends revising.

Figures mirrored from USACE RIBITS · ORM · RRS · synced

The read

A bank clears the regulator here in about 10 months — and takes roughly 1.9 years end to end.

Measured against the national median, the regulator clock sits level with it (1.01×) and the full clock sits level with it (0.96×).

Regulator clock
306days, median
Draft instrument to decision
n = 11 banks · IQR 230–371
Full clock
694days, median
First public notice to decision
n = 14 banks
Vs national
Regulator: North Atlantic 306 days; National 303 days. Full: North Atlantic 694 days; National 723 days
RegulatorFull
Coverage

Regulatory districts, shaded by review time

Review time by district

5 districts
Review time by district, 5 rows
CodeDistrictRegulator clockFull clockBanks
CodeNAONorfolkRegulator clock354 daysFull clock757 daysBanks10
CodeNABBaltimoreRegulator clocknot enough dataFull clocknot enough dataBanks1
CodeNAENew EnglandRegulator clocknot enough dataFull clocknot enough dataBanks1
CodeNANNew YorkRegulator clocknot enough dataFull clocknot enough dataBanks0
CodeNAPPhiladelphiaRegulator clocknot enough dataFull clocknot enough dataBanks2
Supply

Credits available across the division

Wetland
213,325credits
+2.4%year on year
Stream
215,392credits
+23.4%year on year
Demand

Permit applications by district

5 districts
Permit applications by district, 5 rows
CodeDistrictApplicationsOpenShare of division
CodeNAONorfolkApplications17Open1Share of division28%
CodeNAENew EnglandApplications15Open3Share of division25%
CodeNANNew YorkApplications14Open2Share of division23%
CodeNABBaltimoreApplications10Open1Share of division16%
CodeNAPPhiladelphiaApplications5Open2Share of division8%

Recent federal permit applications on public notice

6 most recent of 61
Applications recorded
61since 2026-07-02
Standard permits & EIS · across 5 districts
Open for comment
9of 61
The rest have closed, and remain pending
Recent federal permit applications on public notice, 6 rows
AppliedDistrictProjectComment period
Applied2026-09-24DistrictNAEPinehaven Preserve - Brunswick ME
Pinehaven Preserve project notice, Brunswick, Mainemore

Pinehaven Preserve - Brunswick ME

Comment periodOpen · to 2026-10-09
Applied2026-09-24DistrictNAPDRBA Lewes Ferry Terminal Dredging SX
Maintenance dredging at Lewes Ferry Terminalmore

The applicant is requesting a DA permit to conduct maintenance dredging at the Lewes Ferry Terminal located at 43 Cape Henlopen Drive in Lewes, Sussex County, Delaware. Specifically, mechanical maintenance dredging of approximately 50,945-cubic yards of accumulated sediment from a 3.45-acre area at the Lewes Ferry Terminal basin to a depth of -11.0-feet MLW plus 1.0-foot of overdredge within the main basin and access channel, and to -8.0-feet MLW plus 1.0 foot of overdredge at the C-4 area of the ferry terminal is proposed. All dredged material is proposed to be placed into scows and transported for disposal at White's Basin in Logan Township, New Jersey.

Comment periodOpen · to 2026-10-09
Applied2026-09-23DistrictNANNew York City Economic Development Corporation - Pier 1 Staten Island
Rehabilitation of existing pier and wharfmore

New York District has received an application for a Department of the Army (DA) permit pursuant to Section 404 of the Clean Water Act (33 U.S.C. 1344), Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. 403). Rehabilitation of an Existing Pier and Wharf

Comment periodOpen · to 2026-10-23
Applied2026-09-22DistrictNAPHEREFORD INLET MARINA CM
Maintenance dredging and dock structure placement approvalmore

to perform mechanical maintenance dredging, receive after-the-fact approval for the prior placement of structures, and receive approval for the proposed placement of new structures.

Comment periodOpen · to 2026-10-22
Applied2026-09-15DistrictNAOMNZ07 Wellington Data Center
Wellington data center construction, wetland and stream fill, Prince William Countymore

The applicant proposes to construct the MNZ07 Wellington Data Center on approximately 123 acres in Prince William County, Virginia. The project includes two one-story data center buildings and associated infrastructure, including an electrical substation, utilities, stormwater systems, access, and supporting facilities. DA authorization is required for the discharge of fill material into waters of the United States associated with site grading and construction. The proposed activity would permanently impact 955 linear feet (0.14 acre) of intermittent stream, 1.82 acres of palustrine emergent wetlands, and 0.13 acre of palustrine forested wetlands associated with Broad Run. The project is located east of University Boulevard, south of Interstate 66, and north of Wellington Road at Latitude 38.793943, Longitude -77.581532, in Prince William County, Virginia.

Comment periodOpen · to 2026-10-15
Applied2026-09-15DistrictNAEVictor Ballestas / Greenwich Cove Marina Warwick RI
Marina expansion, mooring field removal, 30 added slipsmore

The applicant is requesting a DA permit to authorize the modification and expansion of an existing commercial/recreational boating facility by extending the authorized Marina Perimeter Limit (MPL) approximately 200 feet to the north into an existing municipal mooring field and adding 30 vessel slips, increasing total berthing capacity from 165 configured slips to 195 slips. The authorized vessel capacity would increase from 186 to 195 vessels. To facilitate navigation and maintain existing customer levels, 30 active municipal moorings within the expansion footprint would be permanently removed. Specifically, the applicant seeks authorization for: -The installation of a 200-foot-long by 8-foot-wide commercial floating main dock extension ("B Dock") supporting twelve (12) 4-foot-wide by 40-foot-long finger floats (22 total slips for vessels up to 40 feet). -The installation of a 200-foot-long by 12-foot-wide commercial floating main dock extension ("C Dock") supporting four (4

Comment periodOpen · to 2026-10-15
Pipeline

Banks proposed on public notice

5 most recent of 15
Proposals recorded
15since 2026-07-02
Bank, ILF and instrument proposals
Open for comment
0of 15
The rest have closed, and remain in review
In RIBITS review
7pending banks
Separate feed — RIBITS bank status
Banks proposed on public notice, 5 rows
AppliedDistrictTypeProposed bankComment period
Applied2026-08-16DistrictNAOTypeBank prospectusDEVMBAWinky's Wetland Mitigation Bank / Hanover
Agricultural land restoration and ditched forested wetland preservationmore

The Sponsor is proposing to restore areas which are currently in agricultural production and preserve and enhance ditched forested wetlands. The Sponsor proposes to generate a total of 35.19 wetland credits.

Comment periodClosed · to 2026-09-15
Applied2026-08-05DistrictNAOTypeBank prospectusDEVMBAWestpark Passive Park
Westpark single-user wetland mitigation bank, Loudoun Countymore

The sponsor, Loudoun County Board of Supervisors, proposes to establish the Westpark Wetland Mitigation Bank as a single-user bank to offset its non-tidal wetland and stream impacts authorized as part of future federal and state permits. The purpose of this notice is to solicit comments and recommendations from the public, federal, state, and local agencies and officials, Indian tribes, and other interested parties concerning the work as described below. All work is to occur in Loudoun County, Virginia. It is a single-user bank, with proposed credits only for Loudoun County's use and with a geographic service area limited only to Loudoun County.

Comment periodClosed · to 2026-09-05
Applied2026-08-04DistrictNAPTypeBank prospectusDEVMBANaturion Hetrick Farms Mitigation Bank BE
Naturion mitigation bank, Berks County, Pennsylvaniamore

The sponsor, Naturion, has proposed a mitigation bank (pursuant to regulations at 33 CFR 332) in Jefferson Township, Berks County, Pennsylvania. Work involves restoration and enhancement of streams and wetlands. The purpose of the proposed project is to provide offset for future impacts to resources regulated under Section 404 of the Clean Water Act, Section 10 of the Rivers & Harbor Act, and Chapter 105 under Title 25 of Pennsylvania Code. Public comments are requested by May 27, 2026. More details are available in the Public Notice Document.

Comment periodClosed · to 2026-09-03
Applied2026-08-04DistrictNAOTypeIn-lieu-fee proposalDEVINLIEUAThe Nature Conservancy SWMP CB-23 Point Breeze In-Lieu Fee Site
114-acre wetland mitigation bank restoration and preservationmore

The Sponsor is proposing wetland restoration, enhancement and preservation activities as well as buffer restoration and preservation on a 114-acre portion of the property. The Sponsor proposes to generate a total of 39.51 non-tidal wetland credits for the purpose of providing off-site compensatory mitigation for unavoidable impacts to waters of the U.S. associated with DA permits within the proposed Geographic Service Area (GSA).

Comment periodClosed · to 2026-09-10
Applied2026-07-30DistrictNAETypeILF instrument modificationMODVT ILF Program Sponsored by Ducks Unlimited
Ducks Unlimited Vermont ILF Program addition, Batten Kill sitemore

This notice announces a request to modify the Ducks Unlimited, Inc. Vermont In-Lieu Fee (ILF) Program Instrument with the addition of the Batten Kill Mitigation Site in the Upper Hudson Service Area.

Comment periodClosed · to 2026-08-28
Approvals

Banks finalized in this division

Banks finalized in this division, 1 row
DecisionDistrictBankStatus nowCredits released
Decision2026-09-22DistrictNABPatapsco River Mitigation Bank - Barrow SiteNAB-2021-397Status nowPendingCredits releasednone yet

About the data on this page

Bank details, status and credit balances are mirrored from the USACE RIBITS registry, the federal public record for mitigation banks. Single-client banks are excluded from supply figures. Credit balances count only banks that can sell today — sold-out, suspended, terminated, withdrawn, closed-out and not-yet-approved banks are left out. Credit classes offset different resources and are never added together. Totals across many banks are rounded to whole credits — a single bank’s own balance never is. Approval timelines come from the USACE permit-processing record (ORM). We calculate the median from every bank’s milestone dates in the division. Full clock means from the first public notice of the prospectus to the final decision — it includes the applicant’s own time. Regulator clock means from the complete draft instrument being received to that same final decision — the part the Corps controls. A median is shown only where at least four banks have both milestone dates. In-lieu fee instruments are excluded throughout. Public notices come from the USACE Regulatory Request System (RRS). Notice text is the Corps’ own; the one-line summary beside it is an AI generated summary.

The map on this page is drawn live from the EPA NEPAssist RIBITS MapServer when you load it.

How these figures are builtReport an issue