USACE mitigation bankingNorth Atlantic Division
How long the NAD division's districts take to approve a mitigation bank, what credit supply they oversee, and how the districts differ from one another. The clock that matters is the regulator's own — everything else includes time the applicant spends revising.
Figures mirrored from USACE RIBITS · ORM · RRS · synced
A bank clears the regulator here in about 10 months — and takes roughly 17 months end to end.
Measured against the national median, the regulator clock sits level with it (1.06×) and the full clock runs 0.82× it — faster than the country.
n = 28 banks · IQR 206–371
n = 20 banks
Regulatory districts, shaded by review time
Review time by district
| Code | District | Regulator clock | Full clock | Banks |
|---|---|---|---|---|
| CodeNAO | Norfolk | Regulator clock308 days | Full clock554 days | Banks24 |
| CodeNAB | Baltimore | Regulator clocknot enough data | Full clocknot enough data | Banks1 |
| CodeNAE | New England | Regulator clocknot enough data | Full clocknot enough data | Banks1 |
| CodeNAN | New York | Regulator clocknot enough data | Full clocknot enough data | Banks0 |
| CodeNAP | Philadelphia | Regulator clocknot enough data | Full clocknot enough data | Banks2 |
Credits available across the division
Permit applications by district
| Code | District | Applications | Open | Share of division |
|---|---|---|---|---|
| CodeNAN | New York | Applications23 | Open6 | Share of division28% |
| CodeNAO | Norfolk | Applications21 | Open3 | Share of division26% |
| CodeNAE | New England | Applications20 | Open4 | Share of division25% |
| CodeNAB | Baltimore | Applications12 | Open2 | Share of division15% |
| CodeNAP | Philadelphia | Applications5 | Open0 | Share of division6% |
Recent federal permit applications on public notice
| Applied | District | Project | Comment period |
|---|---|---|---|
| Applied2026-11-24 | DistrictNAN | Atrium at NavesinkReplace 310-ft bulkhead, pier, and floating dock with 12 finger docksmoreThe applicant is requesting a DA permit to remove the existing wooden pier, aluminum access ramp, floating dock, and all supporting timber piles. The existing 310-linear-foot timber bulkhead will be replaced in place with a new steel sheet pile bulkhead capped with concrete. The project also includes the construction of an approximately 1,242-square-foot timber pier consisting of four connected platforms measuring 6-feet-wide by 12 feet long, 6-feet-wide by 121-feet-long, 6-feet-wide by 32- feet-long, and 6-feet-wide by 48-feet-long.The timber pier leads to a 4-foot-wide by 40- foot-long gangway and a floating dock system totaling 2,232 square feet (SF).The main walkway of the floating dock system will measure 6-feet-wide by 204-feet-long. Perpendicular to this main walkway, twelve floating finger docks will be installed: six (6) measuring 4-feet-wide by 40-feet-long (160 SF each), and six (6) measuring 4-feet-wide by 24-feet-long (96 SF each). | Comment periodOpen · to 2026-12-24 |
| Applied2026-11-24 | DistrictNAE | Riverfront Recapture Inc. RLI Park Project24-acre recreational cove and trail system in public park on Connecticut RivermoreThe applicant is requesting a DA permit to create a 24-acre recreational cove and multi-use trail system within an approximately 60-acre public park development adjacent to the Connecticut River. | Comment periodOpen · to 2026-12-24 |
| Applied2026-11-24 | DistrictNAN | Suffolk County Department of Public Works- Swan River Upland Dike MaintenanceUpland dike repair with 10-year maintenance and periodic beach nourishmentmoreThe applicant is requesting a DA permit, including 10-year maintenance, to repair the previously approved upland dike. The initial work involves excavating 3,000 cubic yards (CY) of clean material from the upland dike, placing 2,300 CY across 26,300 square feet below Spring High Water on the beach in front of the southern dike wall, and stockpiling the remaining 700 CY north of the upland dike. The applicant plans to conduct three (3) additional beach nourishment events within the ten-year maintenance period removing a maximum of approximately 3000 CY per event from the dike and placed within the same placement area in front of the southern dike wall. | Comment periodOpen · to 2026-12-24 |
| Applied2026-11-24 | DistrictNAN | Port Liberty Terminal - Howland Hook/Arthur Kill Navigation Channel WideningWiden area adjacent to Arthur Kill Federal Navigation ChannelmoreThe applicant is requesting a DA permit to widen the area adjacent to the Arthur Kill Federal Navigation Channel. | Comment periodOpen · to 2026-12-24 |
| Applied2026-11-24 | DistrictNAN | Hampton Oyster Company LLCCommercial aquaculture pier constructionmoreconstruction of pier intended for commercial aquaculture use | Comment periodOpen · to 2026-12-24 |
| Applied2026-11-23 | DistrictNAN | Port Authority of New York and New Jersey - Port Newark & Port Elizabeth Maintenance DredginTen-year maintenance dredging of Port Newark and Port Elizabeth berths, 200,000 CY annuallymoreThe applicant is requesting a DA permit to dredge, with ten-years maintenance by mechanical dredge up to 200,000 cubic yards of material from Berths 2-98 at the Port Newark & Port Elizabeth Marine Terminals annually. Dredge depths will range from 35 to 50 feet below the plane of Mean Lower Low Water with two feet of allowable over dredge. Dredged material would be placed into a barge for dewatering. The dredged material would then be amended with Portland cement and transported for disposal at a state approved facility. The total dredge area for all berths is approximately 138 acres. | Comment periodOpen · to 2026-12-23 |
Banks proposed on public notice
| Applied | District | Type | Proposed bank | Comment period |
|---|---|---|---|---|
| Applied2026-11-24 | DistrictNAE | TypeILF instrument modificationMOD | NH ILF ProgramNH ILF program amendment: add Maidstone Bends Conservation Project, Upper Connecticut RivermoreThis notice announces a request to modify the New Hampshire Aquatic Resource Mitigation Fund In-Lieu Fee (ILF) Program Instrument with the addition of the Maidstone Bends Conservation Project in the Upper Connecticut River ILF Program Service Area. | Comment periodOpen · to 2026-12-23 |
| Applied2026-11-19 | DistrictNAE | TypeBank prospectusDEVMBA | VT Beaver Brook Mitigation BankBeaver Brook stream and wetland mitigation bank, VermontmoreThe applicant/sponsor is requesting to establish the Beaver Brook Mitigation Bank to generate compensatory mitigation stream and wetland credits to offset unavoidable aquatic resource impacts permitted within the Vermont Richelieu River Service Area. | Comment periodOpen · to 2026-12-18 |
| Applied2026-11-12 | DistrictNAO | TypeBank prospectusDEVMBA | Guards Shore Mitigation Bank AccomackTidal wetland restoration, preservation, and buffer for 3.79 creditsmoreThe Sponsor is proposing 2.89 acres of tidal wetland restoration, 6.78 acres of tidal wetland preservation, and 0.52 acres of tidal wetland buffer establishment. The Sponsor proposes to generate a total of 3.79 tidal wetland credits upon completion of the activities approved under the mitigation work plan. | Comment periodOpen · to 2026-12-12 |
| Applied2026-11-07 | DistrictNAO | TypeBank prospectusDEVMBA | Hazelwood Mitigation Bank (nee Joyner)/TNTStream and wetland mitigation bank restoration creditsmoreThe Sponsor is proposing 917 linear feet (LF) of stream channel restoration and 734 LF of stream enhancement. The restored/enhanced stream will be protected on both sides by wetland creation areas. The Sponsor proposes to generate a total of 1,622 Unified Stream Methodology (USM) credits upon completion of the activities approved under the mitigation work plan. The Sponsor is proposing 2.88 acres of wetland enhancement, 54.86 acres of wetland restoration, 13.06 acres of wetland buffer restoration, 27.99 acres of upland buffer restoration, 93.14 acres of wetland preservation, and 31 acres of upland buffer preservation. The Sponsor proposes to generate a total of 77.02 wetland credits upon completion of the activities approved under the mitigation work plan. | Comment periodClosed · to 2026-11-22 |
| Applied2026-11-06 | DistrictNAE | TypeILF instrument modificationMOD | NH ILF ProgramNH ILF program amendment: add Williams Property Project, Pemigewasset-Winnipesaukee RiversmoreThis notice announces a request to modify the New Hampshire Aquatic Resource Mitigation Fund In-Lieu Fee (ILF) Program Instrument with the addition of the Williams Property Project in Pemigewasset-Winnipesaukee Rivers ILF Program Service Area. | Comment periodOpen · to 2026-12-06 |
Banks finalized in this division
| Decision | District | Bank | Status now | Credits released |
|---|---|---|---|---|
| Decision2026-11-24 | DistrictNAO | Myrtle Mitigation Bank / Suffolk NAO-2025-1582 | Status nowPending | Credits releasednone yet |
| Decision2026-10-08 | DistrictNAO | Middle James Umbrella Mitigation Bank - Natts Branch SiteNAO-2022-2902 | Status nowApproved | Credits releasednone yet |
| Decision2026-10-08 | DistrictNAO | Middle James Umbrella Mitigation Bank - Clover Hill SiteNAO-2026-1673 | Status nownot in RIBITS | Credits released—no record |
| Decision2026-09-25 | DistrictNAO | Hogue Creek Mitigation Bank NAO-2024-1425 | Status nowPending | Credits releasednone yet |
| Decision2026-09-22 | DistrictNAB | Patapsco River Mitigation Bank - Barrow SiteNAB-2021-397 | Status nowApproved | Credits releasedStream, Wetland |
| Decision2026-09-19 | DistrictNAO | Between the Bridges Mitigation Bank/ClearwaterNAO-2025-792 | Status nownot in RIBITS | Credits released—no record |
| Decision2026-09-18 | DistrictNAO | Horseshoe Mitigation Bank - Phase INAO-2023-2015 | Status nowPending | Credits releasednone yet |
| Decision2026-08-21 | DistrictNAO | Boydton Regional Mitigation Bank / MecklenburgNAO-2024-2544 | Status nowApproved | Credits releasednone yet |
About the data on this page
Bank details and credit balances are mirrored from USACE RIBITS. Supply figures exclude single-client banks and banks that cannot currently sell; credit classes are kept separate.
Approval timelines use USACE ORM milestone dates and exclude in-lieu fee instruments. A median is shown only when enough records carry the dates needed to calculate it.