USACE mitigation bankingPacific Ocean Division

How long the POD division's districts take to approve a mitigation bank, what credit supply they oversee, and how the districts differ from one another. The clock that matters is the regulator's own — everything else includes time the applicant spends revising.

Figures mirrored from USACE RIBITS · ORM · RRS · synced

The read

Too few completed reviews in this division to report a regulator clock.

Regulator clock
—days, median
Draft instrument to decision
n = 0 banks
Full clock
—days, median
First public notice to decision
n = 0 banks
Vs national
Regulator: Pacific Ocean not available days; National 287 days. Full: Pacific Ocean not available days; National 638 days
RegulatorFull
Coverage

Regulatory districts, shaded by review time

Review time by district

1 district
Review time by district, 1 row
CodeDistrictRegulator clockFull clockBanks
CodePOAAlaskaRegulator clocknot enough dataFull clocknot enough dataBanks0
Supply

Credits available across the division

Wetland
2,271credits
+0.2%year on year
Stream
12,291credits
+22.5%year on year
Species
85credits
Demand

Permit applications by district

2 districts
Permit applications by district, 2 rows
CodeDistrictApplicationsOpenShare of division
CodePOAAlaskaApplications23Open6Share of division96%
CodePOHHonoluluApplications1Open0Share of division4%

Recent federal permit applications on public notice

6 most recent of 24
Applications recorded
24since 2026-07-02
Standard permits & EIS · across 2 districts
Open for comment
6of 24
The rest have closed, and remain pending
Recent federal permit applications on public notice, 6 rows
AppliedDistrictProjectComment period
Applied2026-11-19DistrictPOAGreenstreet Investments, LLC., Upper Wasilla Lake, Lot 3 Goddard Subdivision
Fill of 5.45 acres of wetlands for a retail development, reauthorizationmore

Darrel Greenstreet, Greenstreet Investments LLC, stated the purpose is to construct a retail development near existing commercial and retail development. PROPOSED WORK The applicant requests reauthorization to excavate 71,000 cubic yards of silty loam soils eight (8) feet below ground, then backfill with 71,000 cubic yards of clean gravel into 5.45 acres of wetlands on two lots in order to construct a retail development consisting of two buildings, parking areas, and a septic system. On top of the backfilled area, and existing adjacent uplands up to 88,000 CY of clean gravel fill would be placed to raise the ground level to approximately one (1) foot below the adjacent highway. Excavated material would be removed offsite and disposed of in uplands at a gravel pit owned by the applicant approximately 0.25-mile west from the proposed project site. All work would be performed in accordance with the enclosed plan (sheets 1-8), dated May 2016.

Comment periodOpen · to 2026-12-21
Applied2026-11-17DistrictPOAHilcorp Alaska, LLC - Clam Gulch Pad
Fill of 3.5 acres of wetlands for Hilcorp gas drill pad and roadmore

Hilcorp Alaska LLC, Attn: Mr. Stetson Sannes, stated the purpose is to advise the public that the following request associated with the Hilcorp Alaska, LLC Pad Project in Clam Gulch has been submitted for a Department of the Army (DA) permit under the provisions of Section 404 of the Clean Water Act. In EO 14156 the President declared a national emergency under the National Emergencies Act based upon the finding that the United States insufficient energy production, transportation, refining, and generation constitutes an unusual and extraordinary threat to our Nation economy, national security, and foreign policy. PROPOSED WORK: The applicant requests authorization to fill 3.50 acres of palustrine wetlands with 17,572.5 cubic yards of gravel fill for a natural gas drill pad and the widening of an existing access road. The installation of a 2.35-foot by 80-foot culvert would require approximately 188 square feet of gravel fill.

Comment periodOpen · to 2026-12-17
Applied2026-11-16DistrictPOANorth Side Management, Isabella Creek Subdivision
Gravel and peat extraction and fill to finish Fairbanks residential subdivisionmore

To extract and commercially sell mineral materials including sand gravel and peat through the site modification and excavation and to place fill material and finish- grade (specifically lots 21, 32 and 33) property to complete the 45 residential lots for sale in the Bentley Trust North Subdivision in Fairbanks, Alaska. The applicant requests authorization to obtain a new Department of Army (DA) permit to complete the remaining work previously authorized under POA-2004-01127. The applicant proposes to complete the remaining previously authorized activities without changes to the approved project design impacts.

Comment periodOpen · to 2026-12-17
Applied2026-11-12DistrictPOAADOT&PF/Auke Bay East Ferry Terminal Improvements/Auke Bay
Auke Bay Ferry Terminal berthing dolphin and catwalk replacement, Alaskamore

to restore and maintain safe and reliable operations at the Auke Bay Ferry Terminal by replacing deteriorating berthing dolphins and associated catwalks and providing adequate berthing depth at the West berth to accommodate Alaska marine highway system vessels. PROPOSED WORK: The Alaska Marine Highway Service (AMHS) Auke Bay ferry terminal was originally built in 1982. There are currently three AMHS ferry berths in Auke Bay. It is used to moor ships of the Alaska Marine Highway System that transports passengers, including goods and services throughout south and southeast Alaska. The dolphins have undergone several repair projects and are currently in need of full replacement to keep the facility safe and usable for the AMHS vessels that frequent the facility. The piles at the dolphins are severely corroded and in some locations the piles have open holes as a result of section loss. The timber fendering system on the dolphins is also severely rotted and beginning to loosen.

Comment periodOpen · to 2026-12-14
Applied2026-10-30DistrictPOANorth Side Management, Isabella Creek Subdivision
Rock storage and equipment laydown expansion at Pogo Mine's 1380 portalmore

Northern Star (Pogo) LLC (POC: Michael Eckert), stated the purpose is to expand existing facilities at the Pogo Mine for non-mineralized rock storage and associated material and equipment laydown adjacent to the existing 1380 portals. The portals have already been constructed; the proposed work concerns the adjacent rock-storage and laydown expansion. No diversion, relocation, or channel modification of Liese Creek is proposed. PROPOSED WORK: The proposed work is a modification of activities previously authorized under POA-1996-00211. An additional total of approximately 9.18 acres of wetlands would be permanently impacted by the proposed project to construct a new rock storage area next to the 1380 portal. Additional rock will be placed in wetlands adjacent to the existing laydown and storage area. A new stilling basin will be excavated along with a drainage ditch system to capture all runoff from the rock and storage pads. Stormwater from the new storage area will be collected and di

Comment periodOpen · to 2026-12-01
Applied2026-10-30DistrictPOASumitomo - Pogo Mine, Goodpaster River
Pogo Mine rock storage and laydown area expansionmore

Northern Star (Pogo) LLC (POC: Michael Eckert), stated the purpose is to expand existing facilities at the Pogo Mine for non-mineralized rock storage and associated material and equipment laydown adjacent to the existing 1380 portals. The portals have already been constructed; the proposed work concerns the adjacent rock-storage and laydown expansion. No diversion, relocation, or channel modification of Liese Creek is proposed. PROPOSED WORK: The proposed work is a modification of activities previously authorized under POA-1996-00211. An additional total of approximately 9.18 acres of wetlands would be permanently impacted by the proposed project to construct a new rock storage area next to the 1380 portal. Additional rock will be placed in wetlands adjacent to the existing laydown and storage area. A new stilling basin will be excavated along with a drainage ditch system to capture all runoff from the rock and storage pads. Stormwater from the new storage area will be collected and di

Comment periodOpen · to 2026-12-01
Pipeline

Banks proposed on public notice

Proposals recorded
0since 2026-07-02
Bank, ILF and instrument proposals
Open for comment
0of 0
Nothing recorded in this window
In RIBITS review
0pending banks
Separate feed — RIBITS bank status

No bank or in-lieu-fee proposals were on public notice in this division between 2026-07-02 and 2026-11-26.

Approvals

Banks finalized in this division

No banks were finalized in this division in the six months prior to 2026-11-26.

About the data on this page

Bank details and credit balances are mirrored from USACE RIBITS. Supply figures exclude single-client banks and banks that cannot currently sell; credit classes are kept separate.

Approval timelines use USACE ORM milestone dates and exclude in-lieu fee instruments. A median is shown only when enough records carry the dates needed to calculate it.

Public notices come from USACE RRS; MitiVision’s one-line notice labels are AI-generated summaries of the Corps’ text.

How these figures are builtReport an issue