USACE mitigation bankingSouth Pacific Division
How long the SPD division's districts take to approve a mitigation bank, what credit supply they oversee, and how the districts differ from one another. The clock that matters is the regulator's own — everything else includes time the applicant spends revising.
Figures mirrored from USACE RIBITS · ORM · RRS · synced
A bank clears the regulator here in about 3.7 years — and takes roughly 3.7 years end to end.
Measured against the national median, the regulator clock runs 4.70× it and the full clock runs 2.13× it.
n = 1 banks · IQR 1,349–1,349
n = 3 banks
Regulatory districts, shaded by review time
Review time by district
| Code | District | Regulator clock | Full clock | Banks |
|---|---|---|---|---|
| CodeSPK | Sacramento | Regulator clocknot enough data | Full clocknot enough data | Banks2 |
| CodeSPN | San Francisco | Regulator clocknot enough data | Full clocknot enough data | Banks1 |
Credits available across the division
Permit applications by district
| Code | District | Applications | Open | Share of division |
|---|---|---|---|---|
| CodeSPN | San Francisco | Applications5 | Open1 | Share of division36% |
| CodeSPA | Albuquerque | Applications4 | Open1 | Share of division29% |
| CodeSPL | Los Angeles | Applications3 | Open0 | Share of division21% |
| CodeSPK | Sacramento | Applications2 | Open0 | Share of division14% |
Recent federal permit applications on public notice
| Applied | District | Project | Comment period |
|---|---|---|---|
| Applied2026-11-05 | DistrictSPA | Cascade VillageCascade Village wetland fill for residential developmentmoreThe Cascade Village Tracts A1-B1 project requires Corps authorization to permanently fill 1.97 acres of palustrine emergent marsh (PEM)/ wet meadow wetland and palustrine scrub shrub (PSS)/PEM mix wetlands for development of building foundations, residential yards and road infrastructure. The project would also temporarily impact 0.07 acre of PEM wetland for the installation of utility infrastructure (water, sewer, and storm sewer). | Comment periodOpen · to 2026-12-05 |
| Applied2026-10-28 | DistrictSPN | Martinez Renewable Facility (formerly Tesoro Golden Eagle Refinery)Closure of five waste management units at Martinez RefinerymoreThe Tesoro Refining & Marketing Company LLC has applied to the U.S. Army Corps of Engineers (Corps) San Francisco District, for a 10-year Department of the Army Permit to implement closure of the five WMUs (10/11/14, 31, and 32) compliant with the terms of regulatory orders issued by the RWQCB and USEPA, approximately two miles east of the Benicia-Martinez Bridge and Interstate 680, at the north end of the Martinez Refinery (formerly the Golden Eagle Refinery), in Contra Costa County, California. Closure activities at each of the WMUs would consist of some combination of: (1) consolidating waste material into a smaller footprint for placement of a final cap; (2) backfilling excavated areas resulting from consolidation or removal activities with clean soil and revegetating; (3) processing or amending waste materials to improve its engineering properties for transport and/or supporting an overlying cap; and/or (4) covering the waste with a permanent Title 27 multi-layer cap or a RWQCB-a | Comment periodOpen · to 2026-11-27 |
| Applied2026-10-26 | DistrictSPA | Cottonwood Creek channel improvementsCottonwood Creek channel realignment and bank stabilization near Colorado SpringsmoreThe U.S. Army Corps of Engineers (Corps), Albuquerque District, has received an application from James Morley of Morley Companies requesting Department of the Army authorization pursuant to Section 404 of the Clean Water Act for proposed work affecting wetlands and stream channel associated with Cottonwood Creek in unincorporated El Paso County, Colorado. The proposed project involves realigning and stabilizing approximately 1,300 linear feet of Cottonwood Creek to address ongoing channel degradation and erosion associated with increased stormwater runoff. The proposed work includes construction of a meandering stream channel, widening of the floodplain, installation of three drop structures, placement of riprap bank protection, and associated grading. The applicant proposes permanent impacts to approximately 0.609 acre of wetlands and 0.28 acre of stream channel, totaling approximately 0.889 acre of aquatic resource impacts. | Comment periodClosed · to 2026-11-25 |
| Applied2026-10-23 | DistrictSPL | Port of San Diego (WRDA) Beach and Shoreline Improvements for Harbor ParkHarbor Park shoreline resiliency, revetment and salt marsh creationmoreThe applicant is requesting a DA permit to construct the project which consists of rock revetment modification, beach improvement, and creation of a salt marsh to improve resiliency, safe public access, and recreational opportunity along the future Harbor Park shoreline. The project consists of 14.6 acre of redevelopment of the western portion of the existing Bayside Park adjacent to San Diego bay, to what will become the Harbor Park. Detailed descriptions of each project component are included in the attached permit application and supporting documents. The project consists of 4 components, all with the goal of improving the quality of the park shoreline for structural integrity, public access, and environmental quality. The High Tide line (HTL) for the above components is 7.71 ft. MLLW (Mean Lower Low Water) and the Mean High-Water mark is 4.99 ft. MLLW for Corps jurisdiction The specific actions and goals for each project component are listed below which are related to a sea leve | Comment periodClosed · to 2026-11-20 |
| Applied2026-10-16 | DistrictSPK | Timpanogos Sanitary Sewer DistrictWastewater pump station and pipelines on Utah Lake shorelinemoreTSSD has applied for a permit to place dredged or fill material in approximately 24.34 acres of waters of the United States to construct a wastewater pump station, pipelines, and road extensions. The approximately 109-acre project site is located along the northeastern shore of Utah Lake, Latitude 40.3483, Longitude -111.8044; Utah County, Utah, and can be seen on the Pelican Point USGS Topographic Quadrangle. | Comment periodClosed · to 2026-11-16 |
| Applied2026-10-16 | DistrictSPN | McKenzie Bar Gravel ExcavationGravel extraction on McKenzie bar, Middle Fork Eel RivermoreProject would be to continue gravel extraction operations on the McKenzie bar, Middle Fork Eel River, Mendocino County. | Comment periodClosed · to 2026-11-13 |
Banks proposed on public notice
| Applied | District | Type | Proposed bank | Comment period |
|---|---|---|---|---|
| Applied2026-11-02 | DistrictSPA | TypeBank prospectusDEVMBA | Muddy Creek Mitigation BankMuddy Creek Mitigation Bank prospectus, 114.5 acres, Grand County, ColoradomoreThe Albuquerque District of the U.S. Army Corps of Engineers (Corps) has received a prospectus for the proposed Muddy Creek Mitigation Bank, pursuant to 33 CFR 332.8(d)(2). The proposed mitigation bank would include a 114.5- acre area that includes portions of Muddy Creek, Milk Creek, and associated wetlands, located approximately 19 miles northwest of the Town of Kremmling, at latitude 40.303987, longitude -106.551948, Grand County, Colorado, Colorado Headwaters 8- digit Hydrologic Unit Code (HUC) 14010001.lThe purpose of this public notice is to solicit comments from the public regarding the work described below. A copy of the Muddy Creek Mitigation Bank prospectus is available for review on the Regulatory In-lieu Fee and Bank Information Tracking System (RIBITS) website. https://ribits.ops.usace.army.mil/ords/f?p=107:278:16861153846164:::278:P278_BANK_ID:7546 The Albuquerque District will receive written comments on the proposed work, as outlined above, until December 2, 2026. | Comment periodOpen · to 2026-12-02 |
| Applied2026-10-16 | DistrictSPK | TypeILF instrument modificationMOD | East Contra Costa County Habitat Conservation Plan/Natural Community Conservation PlanEast Contra Costa ILF program modification adding two project sitesmoreThe East Contra Costa County Habitat Conservancy has requested a modification to the East Contra Costa In-lieu fee (ILF) program instrument to incorporate the Horse Valley and Vaquero Farms In-lieu fee (ILF) projects. The proposed Horse Valley ILF project is located on Roddy Ranch Preserve, off Empire Mine Road at 5851 Horse Valley Road in Section 18, Township 01 North, Range 02 East and Section 13, Township 1 North, Range 1 East; at Latitude 37.9364 and Longitude , -121.8022; in Antioch, Contra Costa County, California. The Vaquero Farms ILF project is located off Vasco Road, in Section 3, Township 1 North, Range 3 East, at Latitude 37.8306, Longitude -121.6225, near Byron, Contra Costa County, California. | Comment periodClosed · to 2026-11-15 |
| Applied2026-10-15 | DistrictSPK | TypeBank prospectusDEVMBA | Lazy K Ranch Mitigation BankLazy K Ranch mitigation bank proposal in Madera/Merced CountiesmoreLazy K Ranch, LLC has applied for approval of a mitigation bank. The approximately 541-acre bank site is located adjacent to South Santa Fe Avenue on the west, Avenue 28 on the south, and Marguerite Road on the north, approximately five miles east-northeast of Chowchilla, in Madera and Merced Counties, California at approximately Latitude 37.16337, Longitude -120.15301. | Comment periodClosed · to 2026-11-14 |
| Applied2026-09-24 | DistrictSPK | TypeBank prospectusDEVMBA | Wild Flower Mitigation BankDraft Bank Enabling Instrument for Sacramento District mitigation bankmoreThe Sacramento District of the U.S. Army Corps of Engineers (Corps) has received a draft Bank Enabling Instrument (DBEI) for a Department of the Army mitigation bank pursuant to 33 CFR 332.8(d)(2). The purpose of this public notice is to solicit comments from the public. | Comment periodClosed · to 2026-10-24 |
| Applied2026-09-16 | DistrictSPK | TypeILF instrument modificationMOD | Sacramento District California In-Lieu Fee ProgramFresno Slough in-lieu fee mitigation site, 59.17 creditsmoreNational Fish and Wildlife Foundation has applied for Department of the Army approval to establish the Fresno Slough (KIN-1/SAJ-2) project for the Sacramento District California In-Lieu Fee (ILF) program. The proposed project would generate up to 59.17 aquatic resource credits. The proposed in-lieu fee project site is located south of the Little San Joaquin River and East of Fresno Slough in Sections 28, 29,32, and 33 of Township 13 South, Range15 East; at Latitude 36.7615 and Longitude -120.3465; approximately 2.3 miles south of the town of Mendota in Fresno County, California. | Comment periodClosed · to 2026-10-16 |
Banks finalized in this division
| Decision | District | Bank | Status now | Credits released |
|---|---|---|---|---|
| Decision2026-08-11 | DistrictSPK | Cache Slough Mitigation BankSPK-2022-357 | Status nowApproved | Credits releasedMixed |
| Decision2026-06-25 | DistrictSPK | Johnson Cosumnes Mitigation BankSPK-2023-103 | Status nowApproved | Credits releasedWetland, Stream |
About the data on this page
Bank details and credit balances are mirrored from USACE RIBITS. Supply figures exclude single-client banks and banks that cannot currently sell; credit classes are kept separate.
Approval timelines use USACE ORM milestone dates and exclude in-lieu fee instruments. A median is shown only when enough records carry the dates needed to calculate it.
Public notices come from USACE RRS; MitiVision’s one-line notice labels are AI-generated summaries of the Corps’ text.